Earned value cost & Actual cost not coming same??

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi John,

Earned Value and Actual Cost is totaly different. There are a lot of topics discussed regarding EV in this forum.



EV is also known (BCWP) Budgeted Cost for Work Performed while Actual Value is the physical value of the progress or (ACWP) Actual Cost of Work Performed. (Click link below as one of the discussion related to EV)

Schedule % Complete Post #17



If you need to reflect actual cost = earned value for other reason you need to set % Complete type = Labor Unit and Duration Type = Fixed Duration and Unit.

This setting will automate your actual unit = budget labor unit * % complete = Earned Value. Even the duration change it will retain the budget unit the same.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts