How do tie together the P6 Schedule, Submittal Schedule Log, & the SOV? they have redundant info - a code?

How do tie together the P6 Schedule, Submittal Schedule Log, & the SOV?  they have redundant info - a code?  A code could tie them together but how?  Sometimes multiple schedule items belong to only one SOV and vice versa - you could put the sched id in the sov and the sov number in the schedule but couldn't there be one similar code?  I think InEight might do something like this but I am not sure.

R
Rodel Marasigan 👤 Member for 19 years 7 months

The SOV and CBS is defined under Cost Account and assigned into Resources of each activity. WBS is also define separately under WBS module. You can assign multiple resources into activity with different cost account and same thing with activity, you can assign Cost account into single resource assigned to multiple activity.

See below sample for your reference.

Cost-Account

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts