If the scope of an EPC project consists of 100 items, big and small, how does the planner include it in the master schedule?
thanks
If the scope of an EPC project consists of 100 items, big and small, how does the planner include it in the master schedule?
thanks
Might also be of interest the following links:
on option is to make samller schedules and then when importing select the master schedule and during the importing process select add to existing project instead of creat a new project.
Hi Sharjeel,
Depending on how the master schedule is setup and what is the company policy and procedures for Master Schedule.
Some company procedure requiring Level 3 for integrated Master Schedule and Level 4 & Level 5 for contractors schedule.
You can code the contractor's level 4 or level 5 to match Master Level 3 schedule for easy update.