On Same Data Date Actual Units Doesn't Equal Cum AtCompletion Units

R
rauf kensuk 👤 Member for 6 years 5 months

Hi All,

Once a week, i update and schedule my P6. This week I noticed that some of activities' Total Actual Units doesnt Equal for the same week Cum At Completion Labor Units.

In my case they all should be the same, I think (Because my Budgeted Labor Units equals At Completion ( there s tiny difference that I avoid)

In English name of the Activities

-Rough Construction Works (CW)

-Interior CW

-Facade CW

-Mechanical CW

-Electrical CW

-Escalator CW

-Elevator CW

-Landscape CW

 

Data Date 22.Aug.21

First Day of The Week is Monday

Percent Comp. Type is Unit

Duration Type is Fixed Duration&Units

resim_2021-08-24_102724.png

[[wysiwyg_imageupload::]]

R
rauf kensuk 👤 Member for 6 years 5 months

I found the problem. Some acitivities in progress have 0-zero- Rem duration. This causes a problem.

R
rauf kensuk 👤 Member for 6 years 5 months

I found the problem. Some acitivities in progress have 0-zero- Rem duration. This causes a problem.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts