Creating Resource Curves for Labour Loading Profiles

 

Hello All,

I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.

Enterprise > Resource Curves > Add or Modify.

[[wysiwyg_imageupload:7689:]]I have a 3 month duration activity with a budget spend profile of 25%, 50%, 25% but when I set the Resource Curve profile as shown, it ends up front loading all the labour in the first month.

[[wysiwyg_imageupload:7690:]]How do I make this work?

Thanks,

 

Rod

Z
Zoltan Palffy 👤 Member for 16 years 10 months

do you have more than 1 resource assigned to this activity ?

is the resource on the correct calendar ?

what is the duration tyoe ?

R
Rodney Jones 👤 Member for 13 years 11 months

Hi Zoltan, YEs, Applied at the Activity level when the Resource was assigned and then Recalced the project.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Sorry I just have to ask did you assign this resource CUVREe to that activity ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts