How to link Percent Complete to Progress Periods

Good morning everyone,

I would like to link the Percent Complete to the Progress Period so that when I am looking at each Progress Period, the Percent Complete entered will reflect that Progress Period. This relationship is present with the Progress Period dropline, so that if I display ultiple Progress Period droplines, they reflect the percentages I entered for the period. But once I enter progress into Percent Complete, this value in the spreadsheet doesn't change when alternating between Progress Periods.

 

Is there anyway to do this?

 

Many thanks,

Cameron

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Cameron,

there is no such Progress Period in MSP as in Primavera P6;

the Progress Line does not store the corresponding data in a field available to the user; therefore, as far as I know, you should use a numeric custom field to key in the Period Performance every time you display a Progress Line

a time consuming process if I can say, and MS Excel would be a more appropriate tool for that

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts