Greetings Planners,
Based on what to estimate the planned progress for a building project that includes sub-structure and super-structure items (steel fixing, shuttering, casting, deshuttering, slab on grade ect.
I have quantities for steel and quantities for concrete and the price can not be the factor to estimate planned progress.
Your help is highly appreciated
Muataz
installation rates should be based on estimated quantities and historial company standards also the number of men that are going to perfom the task.
I can have a task for 80 hours for 1 man to do something whoulcwould be 10 days. However if I put 2 men on that taks it will take 5 days.
It a combination of estimated manhours and the number of men to use on that task.