By default in Primavera P6 8.2 -
The color of the relationship represents:
Ø Red – Critical and therefore a Driving relationship,
Ø Solid Black – Non-Critical Driving relationship and therefore has Free Float,
Ø Dotted Black – Non-Critical Non-Driving relationship and has Free Float, and
Ø Blue – a selected relationship and may be deleted.
But in my computer its showing both driving and non-driving relationship as non-dotted red lines - How to format the relationship display to make Primavera show non-driving relationships as black dotted lines?
And also In General how to Format the Relationships Lines in Primavera P6 Version 8.2?
unless its a small schedue do not show relationships you will have a cluser of lines
All Right - Thanks Dear Tom Boyle
All Right - Thanks Dear Santosh Bhat
Might be a good idea to throw in the Relationship Total Float and Relationship Free Float columns into the relationships tabs in Activity View. I've shown how to do this towards the end of this article here: Relationship Float, and viewing in Primavera P6 | Australasian Project Planning (austprojplan.com.au)
Vikas,
To my knowledge there is no way to reformat relationship lines in P6. Your understanding of what they mean seems incomplete. In particular:
Ø Red – Critical and therefore a Driving relationship,
Ø Solid Black – Non-Critical Driving relationship and therefore has Free Float,
Ø Dotted Black – Non-Critical Non-Driving relationship and has Free Float
Good luck, tom