Baseline from another File or Excel

V
Vasat Tore 👤 Member for 19 years 3 months

Hi everyone,

 

I have 2 TILOS files and I want to set one of them as baseline to the other.

What is the best way to do this?

 

Thanks

V
Vasat Tore 👤 Member for 19 years 3 months

Hi Alexandre,

 

Thank you for your response.

As I came to find out, there doesn't seem to be a way to do it the way I described.

My work around was to save the baseline in TILOS and progress the activities based on the other.

 

Cheers,

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Hi Vasat,

I hoped that somebody had the solution, but I was wrong. I have found nowhere in Tilos the way to copy the schedule of one project to make it the baselin of another one, as it is possible in Primavera or Asta Powerproject

When you baseline a project, my experience is that you can only select activities in the current project.

Did you ask the question to Tilos people?

All the best,

Alexandre

Featured Partner

Top Posters

wilmoahyi
0 posts
jhalluk69
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts
Christopher Ganotice
1 posts
Ola Gbotoso
0 posts
pennyu
0 posts

Our Partners