I have several projects that i open at the same time. I want to sort the projects into a specific order. They are shown in the EPS in the order i want. When i open them all and go the activity view they are in a different order. How can i specify a sort order?

Thank you

Al

A
Al MacLeod 👤 Member for 19 years 3 months

Hi All,

I also found that if you get the project in the correct order in the project view using the project ID as the sort then sort the WBS alphabetically in the activity view they go to the same order as the project view.

Thanks

D
David Kelly 👤 Member for 21 years 7 months

Sorry, that no longer works. It is OK in the activity window, but not the project window. They have had twnty years to get this right. I shall report back if I find a way to properly order projects in version 19

D
David Kelly 👤 Member for 21 years 7 months

With all the projects open, go to the WBS window, Collapse All, and just move them up and down with CTRL-arrow key.

Thanks Oracle, you changed that keystroke sequence. Took me 20 minutes.

S
Santosh Bhat 👤 Member for 21 years 1 month

Try making the first row of your grouping as "EPS/WBS" and uncheck the Indent box.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts