I am making a case for "sequential logic" - not physical related but the logic is not everything can get done at once. Is this a know practice - or am I now making it one. Your thoughts - I have commonly done this but not named it as such. I really dislike a schedule that has 50 submittals all starting the same day with tons of float, I like to stagger the start, but these crazy restrictive specs means that I have to tie them logically when "logically" there is no tie but sequentially there is. Did I just create the term "non related sequential logic"? Is there a better term for this?
I am making a case for "non-related sequential logic"not physical related but the logic is not everything can get done at once.
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Communicating a resource plan by only using effort is not good enough. Most commercially available CPM scheduling software do not consider resource quantity but only effort units. The need for separate fields for resource quantity, workload and effort is not just a matter of convenience it is essential to get resource visibility and reliable leveling. No wonder many schedulers give up with resource leveling to the point many do not even resource load their schedules.
Sometimes resource leveling yields undesired results because the software cannot correctly model resources such as Spatial Resources. If your software is just a new face for CPM of the 1970’s do not expect much functionality. No wonder many schedulers give up.
Santosh,
The term I would use for the concept of placing logic into tasks that isn't based on any physical requirements but is purely discretionary, is "wrong". In my not very humble opinion, relationships between activities should depend on the laws of physics, nothing else.
Vladimir,
"Splitting" is not a term used in P6. In the last ten years I have helped about 50 clients to implement P6, and often support them through deploymnent.Only one uses leveling. The two major reasons are lack of control over splitting, and the lag in FS relationships is always "minimum" and cannot be mandatory.
Hi Santosh,
I understood that such soft logic is not permitted by specs.
Resource leveling is easy workaround and is better because the number of activities that can be done in parallel depends on resource availability.
John isn't asking for a method of how to resequence, he's simply suggesting a term for the concept of placing logic into tasks that isn't based on any physical requirements but is purely discretionary.
Hi David,
in Spider Project if an activity can be splitted is activty property.
Is it possible to permit or to ban activity splitting in P6?
We define workload as the percentage of time a resource is uniformly distributed throughout team execution. If less than 100% we call it partial workload, others call it part-time. Sharing of some resources on part time basis is an everyday issue no scheduler or project manager can overlook.
To assign resources to work part-time on several activities on the same day happens every day in most construction jobs. With partial workload functionality there is no need to split the activities, just make partial workload assigments, so easy, so common, it is elemantary resource management.
In the above schedule the handling of Submittals by GC can start at the same time before resource leveling. After resource leveling Resource A works on the same day on different activities, never more than the available 8 hours per day, the resource leveling engine will delay some activities if need be as not to overload the resource. Splitting of activities for such simple task is not a good idea, with hundreds of submittals manual leveling is nuts.
What Zoltan and Vladimir say.
Resource levelling is the easiest way to control priorities, it is a simple change in the value of the field used to allocate priority for resources.
HOWEVER you have to be careful in P6. It does not offer proper control over interrupting an activity that has started and doing another one of higher priority – we used to call it “splitting” in the last century when Primavera software had some element of control for this.
one way to get fix the all submittals starting at the same time is if you tie a resource to them and let the availabliity of the resource drive whne they can be submitted.
It is wrong for General Contractor to forward some submittals without any review on his part. Most construction contracts state that the General Contractor is responsible to make sure submitted materials and equipment do fit. I have seen materials and equipment specified that do not fits on the space provided. You might argue it is a design error, but you signed a contract that says it is your responsibility to make sure it fits, under the contract terms you are being paid to make this check.
As suggested before make sure you allocate the necessary resources to perform these tasks.
Hi John,
Vladimir has the suggested the best option. Resource loading the schedule and leveling or smoothing. Here is an example how this works.
John, its often referred to as "Soft-logic", but if you're interested in finding out more, look into RDCPM:
RDCPM®, the Relationship Diagramming Method (RDM) variation of the Critical Path Method of schedule analysis focuses on the reason for the relationship between activities and the reason for their overlap1 . It is distinguished from the Precedence version of CPM (PDM) developed by Dr. John Fondahl in 19612 by the inclusion of significant additional information.
Source: Microsoft Word - WP1035_RD-CPM (mosaicprojects.com.au)
If you will create some resource and assign it to all submissions that shall be modeled as activities with some duration, and then run resource leveling for resource created and assigned, your submittals will become sequential automatically.
The sequence can be managed by applying activity priorities.
I don't think that any spec bans resource leveling.