Powerproject - Project Comparison / Forensics?

T
Tim Kempe 👤 Member for 12 years 10 months

Hello All,

I'm a longtime P6 user looking to make the switch to PP (at last!). As I get ready to do so, I would like some best practices for comparing a series of project updates back to previous baseline(s). Is it done within PP or via some other 3rd Party software?

Thanks, Tim

T
Tim Kempe 👤 Member for 12 years 10 months

Thanks Mike,

I'm actually interested in full forensic comparison rather than simply referencing baseline dates - I understand Elecosoft has an add on called Project Comparison? Is that what you use, and if so what do you think of it compared to say Acumen Fuse? or are there other options?

Regards, Tim

T
Tim Kempe 👤 Member for 12 years 10 months

Thanks Mike,

I'm actually interested in full forensic comparison rather than simply referencing baseline dates - I understand Elecosoft has an add on called Project Comparison? Is that what you use, and if so what do you think of it compared to say Acumen Fuse? or are there other options?

Regards, Tim

M
Mike Testro 👤 Member for 20 years 7 months

Hi Tim

Every base date for progress is recorded within the software so that you can trace progress from strt to finish.

THis is invaluable when tracking progress for an EOT claim As Built record.

Good luck with the switch, you won't regret it.

Best regards

Mike Testro

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts