In Asta, how do we filter for “Near Critical” Tasks?

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Hi Steve,

In the View tab, open Filter and click New

Edit the Criteria #1 row, 

Select Specific activity types: tasks, milestones, then Next

Select Float (Slack?) and Criticity, then Next

Click Show activities with specified float (radio button # 4), Total float, Less than, and enter a value in the Duration field

As I am working with PowerProject in French, I hope you will understand my explanations

Alexandre