Exporting Resource Assignment fromp6 to excel

J
Julia O 👤 Member for 7 years 8 months

Hi everyone,

I tried copying the resource assignment from P6 to excel, when i do this the units dont get copied across and the date column dates back to 1990 and my projects starts in 2020.

Not sure what am doing wrong.

Please help.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

where are you going this ?

in the resource assignments up top or on the botton under resource useage spreadsheet ?