Morning all,
I have a schedule and I'm creating another but I need to copy a section of WBS across both using the same ID's. I wouldn't think this a problem as they're different project IDs but P6 keeps renumbering them.
Any ideas if this can be stopped so it keeps the same IDs in both schedules?
Thanks
Thom
Hi Thomas,
I normally do it this way.
Let's say I want to copy a WBS from Project File A to Project File B.
Video detailing the drag technique in Step 3 can be seen in this link https://imgur.com/MsJmiKw
dod you try doing it while in the WBS section NOT the activity section ?
Delay analysts do this every day. It is common when performing basic TIA.
Can you insert a fragnet (separate project schedule) into another project schedule in Primavera P6? – Project Scheduling & Management Consulting
The concept of Fragnets doesn’t exist anymore in P6. It is a feature in P3. In a P3 fragnet, a user can store a set of activities along with their full details such as relationships, codes, costs, resources, etc. and use this stored set to be pasted as an entire group in any number of places with a single click, without having to create the same set again and again. This saved immense time and efforts. One way to do this in P6 is to replicate an entire WBS (or more) and the constituent activities will also be replicated with all the details. If this is supposed to be done across projects, you have to open multiple projects at the same time.
Best Regards, Rafael
Hi Zoltan,
Neither original nor the project I'm copying into have that box checked. It's fine if I use cut and paste but not copy.
I have a work around but surely it shouldn't matter if it's an empty project there's no need to renumber anything.
thanks for your help as always.
Thom
at the Project level go to defaults and make sure that in the auto-numbering section that increament activiy ID based on selected activity IS NOT CHECKED
Hi all,
This is still a problem, simple copy of a WBS structure and all it's activities to a new project but keeping the activity ID's.
I'm using the WBS pane to copy them over but it insists on renumbering for no reason. Under group and sort I seem to have every option but EPS.
I'm sure this used to be a simple operation.
Any help or advice would be gratefully received.
Thanks,
Thom
Hi Raymund,
That's exactly what I'm doing which is why I was confused when it changed all my activity IDs.
thanks,
also make sure that at the project level that under group and sort it is set to EPS
Hi.
Open both Schedule, in WBS pane copy the WBS from 1 Schedule to another. The ACT ID shall be the same from both.
Regards.