Imported Project Without Baseline

Hi,

I have imported a file without its baseline. But I see baseline start/finishes dates are different than project start/finish dates. I checked there is no assigned baseline. I expect if there is no baseline assigned to the project then baseline dates should be equal to project dates.

Could you please explain ?

Regards

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Irfan,

Insert the Planned Start and Planned Finish dates in the gantt chart columns; you should find that these dates are different from Early Start / Finish dates, and the same as Baseline ones.

When a project has no baseline, planned dates are used instead.

Years ago, the P6 guru Ron Winter had published a very interesting paper "Understanding P6 dates"; easy to find on the Internet, as I do not know how to share my local file on the forum

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts