WBS Summary Activites Moving with Data Date

N
Nathan Siva 👤 Member for 12 years 1 month

Hi Experts,

 

I'm Facing an issue, In my schedule, even though some of the WBS summary activities are already started, they are moving with the data date of the schedule.

Every time when I'm changing the data date, WBS summary activites moving forward with the data dates and then I have to revise back to previous dates of WBS Summary.

Kindly advise.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

it is doing what its is supposed to do.

It summarizes ALL activities under that WBS.

It will use the earliest actual start date of any activites under that wbs and the latest finish (not late finish date) date for the  activities under that wbs. 

so if you update the schedule and things move to the right then the wbs summary will move to the right.   

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Nathan,

Please check that the bar for the wbs summary activities is not displaying the remaining duration only, but also the actual duration.

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts