Monthly Mitigation Meetings

T
Tom Turnham 👤 Member for 12 years 9 months

Hi all,

 

I am setting up monthly mitigation meetings with our Subcontractor and was wondering if anyone had a typical agenda they use?

 

Our Subcontractor is very difficult so want to make sure im not missing anything that would come in handy

 

Thanks for your help

Z
Zoltan Palffy 👤 Member for 16 years 10 months

1. Assessment of previous mitigation plan (is this is 1st meeting there will not be any) did things work or not ? Waht was done right what could be improved. 

2. Current Overall status of the Project.

3. Any impediments such as lack of Design, lack of Access, Late Material delivery, Shortage of Manpower, submittals, RFI's or change notices that are hot and have a potential to hold up work.

4. Review of the Current Critical Path and Next weeks path. 

5. Areas that require special attention or that are behind schedule.

6. Key Contractors who will be responsible for the mitigation.

7. Summary plan for mitigation  ie. working longer hours, working more days, more manpower or different logic and or sequence.

8. Set meeting time and date for deep dive of mitigation plan (approx 1 week from this meeting). 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts