Change activity project codes assignments from a User Defined Field using Global Change in Primavera P6

B
Baz Kawar 👤 Member for 14 years 8 months

I am having difficulty using Global Change to set to assign to an activity the Activity Project Code value from a User Defined Field Value, it forces me to mannually enter the Activity Project Code value, Why? it should allow me just to simply to make the code value equal the value in the User Defined Field.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

as always the code defenition must be already setup

once this is done importing values from excel is much easier

why dont you export and activity to excel that has the global code and use it as a templete for importing values back into p6 via excel

S
Santosh Bhat 👤 Member for 21 years 1 month

Baz, do it via Excel Import - will be much easier to do than manually as you already have the values assigned in th UDF fields.

D
David Kelly 👤 Member for 21 years 7 months

Yes, That would be a great idea. I suggested it to Oracle in 2011. Welcome to the club, Baz

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts