Need Guidance on Schedule Risk analysis

I have an updated schedule,

3. some activites are completed.

2. some have started but not completed

3. some not yet started.

I want to run a schedule risk analysis to no my probabilistic completion date. the schedule is not resource loaded.

 

whats the best approach to this

A
Alex Lyaschenko 👤 Member for 14 years 9 months

Hi Ibrahim,

It is importnat which schedudling tool you are going to use. Spider Project would able to produce probability of success (schedule, cost or both) but you would need to have risk data in your schedule.  

Risk data could be presented a number of ways. Two the most traditional:

1. Risk to activity durations;  

2. Risk event. 

In P6 and MSP you would need to use external plugins but they only support Monter Carlo analsyis. 

R
Rafael Davila 👤 Member for 22 years 3 months

Please be reminded that each iteration must be resource-leveled if some resource(s) is (are) limited.  In real life most schedules are resource constrained.  Closing your eyes to the issue of resource usage and availability is not a good idea.

Project Schedule Risk Analysis Simplified

Page 8 - If several activities using the same resource are potentially scheduled at the same time, they may require more of that resource than is available. Resource leveling in CPM pushes one or another resource-using activity out in time so that a resource’s usage does not exceed its availability in any time period.  Because each solution in a risk analysis must at least be feasible, it should not violate any resource limitations that exist.  Each iteration must be resource-leveled if some resource(s) is (are) limited.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts