(This RP seems to be aimed at practicing forensic analysts and those who employ them - i.e. lawyers. It attempts to describe and categorize a large number of forensic, i.e. retrospective, analysis methods, using unconventional terminology. The RP describes some methods that are viewed as less valid among practitioners in some regions, and one criticism is that the inclusion of such methods tends to validate them.)
American Society of Civil Engineers (ASCE) Standard:
(A clear set of 35 guidelines to be used in any analysis methodology, though an explicit methodology is not described. This is aimed at application in USA courts.)
I know I'm a little late to the party but thought it was a good question. I wrote a pretty in-depth article on how I typically approach creating a time extension request when I'm working with the Contractor.
The very first thing that I do is read the Project's Specifications as sometimes that will provide a roadmap for how to prepare the request. Often times however, the specifications are vague and I'm left with developing the impact using general industry acceptable standards. With that, there are two types of delay events: retrospective (backwards looking) and prospective (forward looking). Retrospective analysis, in my opinion, is more complex so I'll save that for another time. I'll assume this is a delay to the project that has either just occurred, or you have enough information to put together a sequence that will occur in the future. Here's how I would approach a time extension in this sort of an instance:
Develop the timeline for the changed scope/delay event. Get a rock-solid sequence where the dates correspond with the project documents that explains how the Contractor was impacted.
Choose the "pre-impacted" schedule file. Identify the starting point to the delay event, and choose the schedule file that takes into account all of the progress on the job right before the delay event kicked off. If this is a forward-looking delay, or it's an impact that you just experienced, you would typically use the progress update that was just submitted.
Insert the delay sequence (from step 1) into the pre-impacted schedule file to see if it had a net effect on any of the contract milestones.
If it did, did it push the milestone passed the contract date? Make sure it's not just float that is being consumed.
Also, is there anything that was happening concurrently that may have also impacted the project? It's a good thing to account for that in the analysis.
If the completion date was pushed beyond the contract date as a result of the delay, then I go ahead and put a write-up together explaining the background of the delay event, the methodology used to develop the analysis, and the actual request stating what the Contractor is seeking (i.e., an "excusable, compensable time extension", or "excusable, non-compensable time extension).
I'll close by saying that because projects are so different, and delays can be very complex, the way in which you communicate the delay to the Owner is going to vary widely project to project. This methodology might work in many cases, but not necessarily in all cases. Keep that in mind when you're putting your request together.
I believe there is no global standard for preparing EOT. Even the type of technique you use can be chosen depends on the type of delays. Most of the time am using Impacted as Planned as it is easier to use though maybe most of Planners who work in the Consultancy will not agree.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
AACE International Recommended Practices:
52R‐06: TIME IMPACT ANALYSIS – AS APPLIED IN CONSTRUCTION (2006 - 9 pages)
(This covers prospective EOT applications like Patrick describes.)
29R-03: FORENSIC SCHEDULE ANALYSIS (2011 - 134 pages)
(This RP seems to be aimed at practicing forensic analysts and those who employ them - i.e. lawyers. It attempts to describe and categorize a large number of forensic, i.e. retrospective, analysis methods, using unconventional terminology. The RP describes some methods that are viewed as less valid among practitioners in some regions, and one criticism is that the inclusion of such methods tends to validate them.)
American Society of Civil Engineers (ASCE) Standard:
ANSI/ASCE/CI 67-17: SCHEDULE DELAY ANALYSIS (2018 - 25 pages)
(A clear set of 35 guidelines to be used in any analysis methodology, though an explicit methodology is not described. This is aimed at application in USA courts.)
Hi Akhil,
I know I'm a little late to the party but thought it was a good question. I wrote a pretty in-depth article on how I typically approach creating a time extension request when I'm working with the Contractor.
https://jobsessions.com/post/8D556D3D-0952-DFF4-3B43-1B6BC7F5D845
The very first thing that I do is read the Project's Specifications as sometimes that will provide a roadmap for how to prepare the request. Often times however, the specifications are vague and I'm left with developing the impact using general industry acceptable standards. With that, there are two types of delay events: retrospective (backwards looking) and prospective (forward looking). Retrospective analysis, in my opinion, is more complex so I'll save that for another time. I'll assume this is a delay to the project that has either just occurred, or you have enough information to put together a sequence that will occur in the future. Here's how I would approach a time extension in this sort of an instance:
I'll close by saying that because projects are so different, and delays can be very complex, the way in which you communicate the delay to the Owner is going to vary widely project to project. This methodology might work in many cases, but not necessarily in all cases. Keep that in mind when you're putting your request together.
Hope that helps! Best of luck.
Pat
Hi,
what is the meaning of contemporaneous schedule baseline update?
I believe there is no global standard for preparing EOT. Even the type of technique you use can be chosen depends on the type of delays. Most of the time am using Impacted as Planned as it is easier to use though maybe most of Planners who work in the Consultancy will not agree.