2. Distribute monitoring sheets to relevant supervisors(capture the relevant information you need to update schedule)
3. Set up the periodical updating date before which u need to receive the item 2.
4. Update the schedule(use baseline your target to check for any slippages)
in the next update, use the prev. update as your one of target schedule to verify any activities slipped from the completion dates, check over all project completion date...
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Few more...
Schedules are mainly tracked on three things
1)Time
2)Resources i.e. Man, Material,Money
3)Site Inspection
The presentation of the these parameters can be done in many forms depending on the level at which are to be presented.
Tracking:
1. Establish baseline programme.
2. Distribute monitoring sheets to relevant supervisors(capture the relevant information you need to update schedule)
3. Set up the periodical updating date before which u need to receive the item 2.
4. Update the schedule(use baseline your target to check for any slippages)
in the next update, use the prev. update as your one of target schedule to verify any activities slipped from the completion dates, check over all project completion date...
many more things to add............
Hi,
What do you mean by HOW TO DO THE TRACKING IN A PROJECT?
Is it MS Project schedule or P3e schedule.
Regards.
Francis,
Brochures and lot of application cases are available on Primavera website.