Expanding Task Usage View

Hi,

Just wondering if there is a simple way to expand each task on the Task Usage View so that it shows individual resources against the task rather than the total for all resources?

In the example below, I have manually expanded task 213 to show the two resources and their hours, but I can't seem to find a way to do this quickly. I've tried using "Outline-Show All Subtasks" but I suspect that this only works with tasks and not resources.

task_usage_view_example_for_pp.jpg

Other than manually opening each task or exporting the information to Excel, is there a quicker way to do this?

Many thanks.

T
Tony McClennon 👤 Member for 23 years 6 months

Tom/Alex,

Thank you for your replies.

It looks as if the problem I am having is a result of filtering out the tasks. It is a five-phase project, and I am populating just one phase.

All of the tasks have a Phase reference in a customised text field, but I noticed when expanding each task that the resource allocations do not, so simply by pasting the phase reference against all of the resources on the task usage view, the problem is solved.

Again, many thanks for taking the time to help - very much appreciated.

T
Tom Boyle 👤 Member for 19 years 6 months

Tony,

It seems your installation may require repair.  Outline-"Show all subtasks" works fine for me as it does for Alexandre - using both MSP 2010 and MSP 2016.  That is, clicking the command in the Task Usage view opens all tasks to view all tasks and their resource assignments. You can also select multiple tasks and use the outline "Show/Hide Subtasks" command to roll the assignments in or out.  Good luck, tom

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Tony,

if you mean that you want to show the detail of one specific task, I suggest that you display the gantt chart in the upper pane of the screen, and the task usage view in the lower pane

then, navigate from task to task in the gantt chart and you will see the detail of the resource assignemnts in the task usage view, exactly the way you describe in your post

Alexandre

T
Tony McClennon 👤 Member for 23 years 6 months

Hi Alex,

Thanks for replying. I can use the "Outline-Show All Subtasks" or "Level X" options to show all the tasks without any problem.

However, if I want to show each of the resources allocated to the tasks below the task name (as per line 213 in the extract above), the only way I can do this is by clicking on the expand arrow against each task (rather like opening out a summary bar).

Unfortunately this is extremely time consuming, and most of the time I am trying to do this, I manage to click outside of the expand arrow and all the resource rows are then hidden again.

Should have mentioned that I am using Project Professional 2016.

Since posting, I have been doing a bit more searching and on previous versions of MS Project, you could apparerently achieve this by using Resource Allocation via an option on the "outline" icon, but which seems to have been removed in MSP 2013/6.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello Tony,

I do not understand where your problemn stands; I have tried on one of my sample projects, "Outline-Show All subtasks", or "Level x" works perfectly in Task Usage

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts