Forecast Schedule

Dear Sirs,

I would like to ask favor/ help for making the Forecast Schedule.

Currently, I already completed the update on our Baseline Schedule to the current cut-off last 24.04.2020.

After I run it , the outcome appears to be a -166 float. With this apprecfiate your help to solve this as my client is already asking.

 

Thank you

 

Regards,

Smoke

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi.

The issue is due to out of sequence. Trace the predecessors of predecessors of predecessors of activities that slips beyond project baseline completion date.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

1. do as Raymund suggest

2 .filter for any selected filter

and select both the 3rd and 4th ones in the list 

has start constraint

has finish constraint

these are activities with hard constraint dates if you do not need them remove them

3. filter for remaining durations over 20 days you could have made a typo in the remaing durations.

S
Smoke Manibo 👤 Member for 7 years 6 months

Thanks for your response.

Actually I already done that and no negative float appears. One thing is that the forecast dates are now way beyond the original project completiion dates. As I trying to change the dates of some activities some are not moving even I have chnage the relationship or changing the lag.

 

Thanks

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

As I understand from you, you want to get rid of the Negative Float (-166).

In the Projects Pane:

1. Select the Project

2. In the Project Details, Select Dates

3. Clear the Date shown in the "Must Finish By"

Or In the Activity Pane:

1. Trace the Activities with -166 Total Float and Clear the assigned Contraints.

 

Hope this will help

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts