I am managing a project for a client.I have claimed EOT, for the weather delays and the Principal Agent( PA) has asked me to support my claims with the critical path analysis (CPA)using MS Project ,Please Help
Thanks , Regards
David
Hi, everyone
I am managing a project for a client.I have claimed EOT, for the weather delays and the Principal Agent( PA) has asked me to support my claims with the critical path analysis (CPA)using MS Project ,Please Help
Thanks , Regards
David
why would not include that with the original EOT submittal how can you possibly submit a claim without it.
he wants to see what the critical path was during tha adverse weather. If it was interior work then there would be no impact due to adverse weather.
The critical should be expalined in the EOT and should state specifically which weather sensititve were impacted.
https://www.slideshare.net/ChrisCarsonFAACEPSPD/84r13-planning-and-accounting-for-adverse-weather