Cant able to chnage outline(indent or outdent) of the Task

N
Nathan Siva 👤 Member for 12 years 1 month

Hi Experts,

I can't able to change outline level (indent or outdent) my project task, I already checked, there is no grouping, Sorting and filter applied.

The project which i'm working have external links

Kindly guide.

G
ghiz mar 👤 Member for 13 years 9 months

Hi Nathan,

Could you please put a screnshot of your workplan, just to understand the issue,

Regards,

Mar

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Nathan,

I hope this will help you:

on image natan1, select Task B and click the tool inside the red square

you should obtain the result in image nathan2.png

alexandre

[[wysiwyg_imageupload:7326:]]

 

 

 

 

 

[[wysiwyg_imageupload:7327:]]

N
Nathan Siva 👤 Member for 12 years 1 month

Hi Alexandre,

Thanks for your suggestion, But I'm still facing the same issue, even after I used indent tool, it's not showing any changes in outline level.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Nathan

I am not sure to understand where your problem stands;

let's do the following

select the second task in the spreadsheet, then in the Task tab of the ribbon click on the Indent tool (the small arrow looking to the right)

as far as I know there is no functionnality ins MS Project to disable indenting/oudenting tasks in a project

All the best,

Alexandre

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb