Hi Experts,
I can't able to change outline level (indent or outdent) my project task, I already checked, there is no grouping, Sorting and filter applied.
The project which i'm working have external links
Kindly guide.
Hi Experts,
I can't able to change outline level (indent or outdent) my project task, I already checked, there is no grouping, Sorting and filter applied.
The project which i'm working have external links
Kindly guide.
Alt+Shift+Right Arrow
Hi Nathan,
Could you please put a screnshot of your workplan, just to understand the issue,
Regards,
Mar
Did you resolve your issue ?
Nathan,
I hope this will help you:
on image natan1, select Task B and click the tool inside the red square
you should obtain the result in image nathan2.png
alexandre
[[wysiwyg_imageupload:7326:]]
[[wysiwyg_imageupload:7327:]]
Hi Alexandre,
Thanks for your suggestion, But I'm still facing the same issue, even after I used indent tool, it's not showing any changes in outline level.
Hi Nathan
I am not sure to understand where your problem stands;
let's do the following
select the second task in the spreadsheet, then in the Task tab of the ribbon click on the Indent tool (the small arrow looking to the right)
as far as I know there is no functionnality ins MS Project to disable indenting/oudenting tasks in a project
All the best,
Alexandre