Hello All,
I have progresss a programme and added some new activities as Rev 08, progressed as at 14-Feb-20
However, my previous progress is Rev 07, which was progressed on the 17-Jan-20.
Can i know if there is a quick method that i can transfer my progress from Rev 08 to Rev 07a?
Many thanks
Mike
open Rev 8 and make rev 7 a baseline
then select maintain baselines and select update
then from here you can choose what to update all activities or a filter or additional update options under Update options
pick and choose what to update
when you are done select Restore to put REV7 back into the selectable projects
Hello Mike,
I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6
Alexandre
Hmnn... not that easy, because i have changed some duration and logic.
I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another
Many thanks
Mike
Don't you just make a copy of Rev 08 and then delete the new activities?