HELP! Leveled Resources Delayed by Years ? WTF?

Member for

22 years 9 months

Hi Jean-Michel,

how can you expect a reasonnable answer with such a few details?

* you should check the resource details, and specifically the Units and Price tab:

the by default Effective date is the 1st of january in the year the resource was created in the database; when the resources are leveled, P6 reschedules the activities according to this date; for example, the activity is scheduled to start dec 10, 2019 prior to leveling, and the resource is only effective jan 1st, 2020; the activity will be rescheduled as from this date after leveling

* you should check also the resource assignments in the other projects in you database

I hope this will help

Alexandre

Member for

15 years 11 months

Hi,

Kindly share the XER file?

 

Regards,