Assigning Resource

Hi, 

 

I want to assign a new resoure an activity. Can i know why it will changed my budgetted unit? I can see my budgetted Activity Cost is 395050 but when i assign a new resource, it splitted or share my bugeted unit. 

 

How do i prevent this from happend when i assign a new resource?

 

Thanks

Mike 

 

 

 

capture.png

Z
Zhang Haixiang 👤 Member for 21 years 1 month

please check "duration Type" 

set to "fixed duration and Units/Time"

and then if you add a new resource, the budget will be calculated as duration*Unit/Time

for example, you have an activity with 10 days duration, and you add a resource A (8.00/day) to it, then the budget will be 10*8=80.

if you add another resource B (4.00/day) to it, then the budget will be 10*4=40, it will not share the budget from resource A

 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

it did nto split your budget what it does by default is if in your resources your max units/time isset to 8 hours per day it multiplies 8 times the duration to get your budgeted manhours. You can then revise the budgeted manhours as needed. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts