I would call it WEIRD math to define duration using dates at one WBS level and sum of values within another WBS level.
What is the logic of this?
Why not inverting the calculation rules?
When you can have multiple calendars and the software calculations are in hours rolling-up days can yield wrong values.
Because the calculations for days are based on averages calculation of duration in days can be misleading. Although never as good as showing durations in hours if you have the urge to show days better show remaining workdays considering every workday duration in hours can be different.
a single activity with a calendar where different days have different work hours.
as you add resource calendars duration in days can get very weird, even if for a single activity.
Adding more activities as well as WBS phases makes it worse at the WBS levels.
For simple calendars and resource loading it make sense to use days as an option to enter activity duration.
It has to do with calendars. Where activities within a WBS group contain a mixture of calendars, the Proejct Default Calendar is used to calculate duration at the WBS Group level.
If you display your calendar column you'll see why.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I would call it WEIRD math to define duration using dates at one WBS level and sum of values within another WBS level.
At the Construction WBS the 36 days are working days from 12/31/2019 to 2/18/2020
At the Structural WBS the 50 days are the total of all of the workings days under that wbs
6+3+8+6+4+5+5+8+5=50
its straight math
Santosh is spot on with his comment. If you change your user preference settings to hours they should match.
What happens if you show all durations in hours?
It has to do with calendars. Where activities within a WBS group contain a mixture of calendars, the Proejct Default Calendar is used to calculate duration at the WBS Group level.
If you display your calendar column you'll see why.