Resource Assignment on Activity Completed or in Progress

Hello, 

 

I am applying resources to the activities in progress or completed but the actual is not showing on the activities that have been completed or in progress

 

Screen 1 - This is before the resource is applied 

1.png

 

Screen 2 - After i applied resource to the activity with original duration 15d, the budgeted labour unit shows 15, remaining labour unit shows 4 which are correct but the Actual labour unit is not showing anything. The actual suppose to show 11 

2.png

Thnaks 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Go to Projects make sure you project is open click on  the Calculations tab on the right under Resource Assignments 

make aure that When updating Actual Units or Costs that 

Subtract Actual from At Completion is checked and that 

Recalculate Actual Units and Costs when duration % complete changes is checked

also make sure that Link Actual and Actual This Period Units and Cost is checked.

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

I do noticed the same issue with some of my Projects. But practically, Actual Unit and Actual Cost must be recorded manually.

You can work around, export the Resource assignment to excel then the actual units equals multiplying the Budgeted Units by the Performance % of the activity. Import back the Resource assigment then you get the actual units and as well the Actual Cost.

 

Regards,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts