Hi All,
Can i know why i can see the resource on each day?
For example, i have 4000 unit assign to activity A1010 but i only can see 800. I have 5 days on that activity so it should be 800, 800, 800, 800, 800
Thanks
Mike

Hi All,
Can i know why i can see the resource on each day?
For example, i have 4000 unit assign to activity A1010 but i only can see 800. I have 5 days on that activity so it should be 800, 800, 800, 800, 800
Thanks
Mike

if it a a LOE it will stack it on the 1st day unless you assign a curve to it
Assign linear resource curve.
Hi,
Thank you for the reply. i checked, it was set to Day. It doesnt show the resource on day on resource assignment tho
[[wysiwyg_imageupload:7170:]]
Many thanks
Mike
Hi, set the resource analysis to daily in the user preferences.