Curved Data Date - why? what? when? is it for?

I am used to seeing a straight data date line. Lately I been seeing curves data date lines, ie curved out around certain activities.  I assume this is from a setting, and after googling it with-out getting an easy answer I am asking you.  What does it represent?  Where is the setting for it?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

click on the crooked progress line icon and it wil be a straigh line.

 

[[wysiwyg_imageupload:7096:]]

 

J
John Reeves 👤 Member for 13 years

OK, not that hard to solve, it is the "Progress Line" which overlays the Data Date line.  Obviously I didn't use it much prior.  I kind of assumed it was something like that but here is a confusing aspect.  I don't have a Baseline attached to that schedule - so how can it be telling me how ahead or behind the dates are - meaning how can the line be crooked?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts