The F9 is Canceled when i close the project

Hi everyone, 

I have a probleme with a project in P6, the dates ( delta of 1 minute but the date change to the day after )  of about 30 activities (30/1600) changes when i close and re open the project. I think that the problem comes from the excel that we import in order to change the ressources. So when i remove the ressources its all ok but, so i try to add the ressources back... same problem

i tried to add another activities with the same sittings it remains the same. 

thanks a lot for ur help!

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to edit user preferences and turn your TIMES ON

when you calculate the schedule make sure to set the DATA DATE TIME to 8:00 am or the earliest times on all of your calendar being used.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts