Doubt P6 - At Complete versus BL Project

Hello,

I have a doubt:

Schedule "A" has an At Complete of 7.94% in July / 19 before being entered as the baseline for Schedule "B".Its Ok for me...But after schedule "A" is entered as baseline on schedule "B" the field "Cum BL Project Nonlabor Units" has a% of 7.61%What am I doing wrong? duvida_2.png

Z
Zoltan Palffy 👤 Member for 16 years 10 months

then get access to it or talk to the adminstrative person who does have rigths to this

H
Helder Rodrigues 👤 Member for 6 years 9 months

Hello Zoltan, 

 

I don't have access to Admin menu 

 

Is there another solution to this problem?  Regards,

H
Helder Rodrigues 👤 Member for 6 years 9 months

Hello Zoltan, 

I don't have access to Admin menu
 
Is there another solution to this problem?
 
 
Regards,
Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to

Admin 

Admin Preferences

go to the Earned Value tab 

at the bottom where it says Earned Value Calculation When calculating value form a baseline use

change this to Budgeted value with current dates or At completion values with current dates 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts