Impacted As Planned (totally ignore as-built dates for completed activities/delay events)?

Member for

19 years 10 months

Hi DJ

You can always find As Built records somewhere.

Do you have access to any of the following:

QA/QC records-Permit to work-Core Test records-site diaries-valuations-delivery notes-

If you genuinely don't have anything then you are truly stuffed.

Best regards

Mike Testro

Member for

15 years 11 months

Dj,

After insertion of New Activities and constraining the start date of impact run the schedule in order to determine the new completion date.

Member for

6 years 2 months

Hi Raymund, these are the steps I did:
1. Insert a valid excusable/culpable delay event to the first original approved programme.
2. Write the no. Of days impact on key dates in culpable and excusable columns.
3. Insert other valid events chronoligacally one by one and tepeat steo 2 per inserted dealy event.
4. Sum up each the culpable column, this will be the eot and add this to original key date and this will be the eot date.

Member for

15 years 11 months

Dj,
Use the as planned. There are always an argument pertaining to claims. Good reasoning will be an advantage.

Regards.

Member for

6 years 2 months

Hi Thanks Mike, what if my project doesnt have any good as built records.

Member for

19 years 10 months

Hi DJ - Welcome to Planning Planet.

You are wasting your time if you submit an impacted as planned analysis without any reference to what actually happened.

Even a Time Impact Analysis is entirely theoretical and of little use.

Concentrate on facts and the application of common sense to tell your story. Keep well away from any mention of a critical path.

Best regards

Mike Testro