Critical bars Display before Baseline

Hi Everybody,

Please clarify this

Why my some actvities are showing Red in Gantt Chart even i didn't make the baseline and not entered the project must by Finish Date.

 

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you must have an end date either on the last activity or project must finish by adte 

M
Muhammad Saqib 👤 Member for 7 years 8 months

I have selected the Longest path option but not given the project finish date. Then why it shows some activites in red bar

Z
Zoltan Palffy 👤 Member for 16 years 11 months

that depends on how you have your critical path defined it can be zero days total float or longest path

if you have it set to zero days. If you do not set a project must finish by date then the late dates will match the early dates and the float will ALWAYS be zero 

Forum Sponsor

Top Posters

Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts