I am using a stand alone version of P6 and have run into an issue with Baselines

I create a baseline for each week to show variance for the work that was planned to be completed that week.   I have just recieved a notice that I have reached the max number of Baselines for the project.  I deleted a few older ones and then created a new one for the current week.   In looking at the variance column for this week I expect to see zero variance and much to my surprise the numbers were from -60days to plus 30 days.  there were a few that were zero but not many.  

Anyone else had this problem and how did you fix it.  

R
Ron Beechey 👤 Member for 10 years 1 month

Thanks for the info 

I am exporting the project and then opening to see if it rids me of the bad dates

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to admin Prefernces 

then Data limits 

then change the Maximum baslines per project to whatever number that you want. 

You can also change the number of Maximum baselines coped with project to whtaever you want. 

R
Rafael Davila 👤 Member for 22 years 3 months

When resource leveling a small schedule variance of an activity can become a cause for substantial rearrangements in the project network, it can change critical path or order of activities.

Out of sequence progress can have a similar effect.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts