I see in P6, based on the default settings at project level, the activity ID gets incremented automatically when we copy an activity. Is there similar setting somewhere for auto incrementing of Project Number at EPS level when we create a project, please?
Autoincrement of Project ID
Forum Sponsor
Top Posters
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
so am I
I am talking about the projects at EPS level. Actually we were exploring an option to auto increment by 10 or defined number whenever we copy and a paste a project. Just to have consistency.
its already built into the program
1st project is lets say called base
if you copy it then the autoincrement name wil be base-1
if you copy that then it will be base-2
and so on but there is no changing the auto increment for a project name whne adding only when coping an existing project
best thing to do os to create your own nameing convention and stick to it