Adding price for activities in order to get a cash flow

Hello,

In my schedule, I didn't add any resources except for some materials.

Now I need cash flow for the project (revenue) on a monthly basis, how I can add prices for the activities ???

I have added the materials in order to get material usage on a weekly, monthly basis. 

I didn't add the labor resources because most of the works are subcontracted.

Regards,

Z
Zoltan Palffy 👤 Member for 16 years 10 months

just add resource for the sub contractors call it lump sum and assign labor $ to each activitiy