I need to have an excel spreadsheet that lists all activities original duraion as well as lags.
I've tried numerous was of P6 exporting to excel, filtering/formatting within P6 to copy and paste in excel, but am unable to find a way to get both the original durations and lags on one spreadsheet.
Does anyone have any ideas? Thanks!
Santosh has the solution
Hi Larry
You can use the 'Reports' feature for all the relationships in the schedule. Also the lags.
Go to Tools < reports and then select report AD-02 activity relationships.
Regards Johannes