Global change not working for baseline programme

I am aware of the need to change the planned start and planned finish of a baseline programme before attaching it to the programme that I am usuing to demonstrate a delay.

However in certain instances the planned dates are not being changed. ie an activity in progress with and actual start of the 30 May 2018 and a finish of the 3 Dec 2018 after running the global change to set the planned dates gives a planned start of the 30 May 2018 but a finish of the 30 Nov 2018 and not the 3 Dec 2018.

I assume that the global change is:

Condition 1 activity complete. planned start=actual start planned finish=actual finish

Condtion 2 activity in progress. planned start=actual start planned finish=finish

Is this correct?

K
Kevin Rayner 👤 Member for 17 years 4 months

You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

how come you are mixing planned start date with finish dates  ?

actual start = planned start

actual finish = planned finish

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts