Primavera P6 - Physical completion % question - I am a beginner

T
Toon Blue 👤 Member for 7 years 5 months

  This is a simple schedule that I have made and I am required to update this schedule every month which is 22 Jan 19.

Please refer to my figure 1 for a simple of this schedule

[[wysiwyg_imageupload:6606:]]

Now i press the F9 function - scheduling after I have enter physical completion 80% for the buying of materials (A1020). Please refer to the picture below (figure 2).

[[wysiwyg_imageupload:6607:]]

Somehow this look strange on the gantt chart. Any advise for this?