Hi Everyone,
I am facing an issue after scheduling (F9) in Primavera.
I am working on a Housing project ( Planning Phase) and i am applying milestones between activities.
When i schedule the project on current data date to give me a updated view of my schedule, all dates appear in my activites is same as data date.
Please help me out in this issue.
Thanks for your help
the only way is can happens is that
1. there are no predecrssors to the milestones.
or
2. all of the predecessors have been completed and the milestones are riding the data date
thats it
Thanks Anoon for your reply.
But i have logically linked all the activities. Still problem is there. :(
First, make sure that your activities were logically linked before pressing F9. Remember, do not enter dates manually, only durations and then play with your mouse for defining logics. Just practice and later on you will enjoy it!