Schedule Percentage complete

A
adab azeez 👤 Member for 9 years 10 months

Greetings to everyone.

Is there any possible technique in primavera to get all the schedule % complete for each day ?

Thanks in advance.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

whats your measuing stick  ? Manhours, dollars units ? or do you not have any.

A
adab azeez 👤 Member for 9 years 10 months

Raymund.
I have calculated this daily budgeted cost from Resource assignment. Then on excel I have done copy and paste. Then added the all budgeted cost. After that divided daily budgeted cost with the total one. And after that I took cummulative budgeted cost too..
But my schedule % calculation is different by 2 or 3 from the primavera schedule percentages.
And unfortunately Unbale to track the fault.entire schudule is resource added.

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi..

Divide the Daily Budgeted Cost by the Project Total Cost then multiply by 100%.

That shows the Daily Schedule % Complete.

A
Anoon Iimos 👤 Member for 19 years 8 months

That's easy, I mean if you were referring to "planned % complete" (meaning - baseline % complete). You can do that automatically anyway you want. Of course you have to move data date at anytime you want, which means that your schedule is progressing exactly as planned. Your "planned dates" shall automatically become "actual dates", everytime you update or move your data date. You can generate a tabular report, showing daily, weekly, monthly or whatever you want.

A
adab azeez 👤 Member for 9 years 10 months

Thank you Anoon,
how would we know all the schedule % complete at a time corresponding to planned dates ?
My project start date is 3 January. And I want to know the schedule% complete for each day. In order to know this I am changing the data date each time and then scheduling it to see the % complete, which is a long procedure. Any shortcut for this ?

A
Anoon Iimos 👤 Member for 19 years 8 months

Yes, if you're planning unit is "day", then for sure you will get your corresponding percent complete per day.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts