Urgent Help Please

A
adab azeez 👤 Member for 9 years 10 months

While scheduling my project, my schedule % complete value increases for few seconds on the screen and later it adopts the previous constant value.

I mean my schedule % complete value is not changing. Any leads please?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

EVERY activity in the schedule MUST have a successor except the last one. 

A
adab azeez 👤 Member for 9 years 10 months

I guess I have fixed it now.
For this I have taken the following three actions.
Probably anyone of these three actions have brought me on the right track.

1. I reduce the price per unit of each resources to 1$/ unit.
2. Many of the equipments' last activities were not having successor . So I assigned a successor.
3. All of the equipment's first activity were sharing same predecessor despite of having internal links between them. So removed all the predecessor except few leading equipments.

May anyone of the above worked for me.

Thank you so much for your support.

S
Sultan Salabat 👤 Member for 9 years 2 months

For Schedule % Percent completion, Check following

1. Make sure your data date is valid

2. Your baseline must be assigned. 

However, for WBS, cost must be assigned to activites.

Check above points and schedule again by pressing F9.

S
Sultan Salabat 👤 Member for 9 years 2 months

For Schedule % Percent completion, Check following

1. Make sure your data date is valid

2. Your baseline must be assigned. 

However, for WBS, cost must be assigned to activites.

Check above points and schedule again by pressing F9.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

dud you update teh schedule ?

if you did update it what % complete type are you using ?

did you change the data date ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts