What would be maximum unit per time (h/d) if my day time resource is 10 helpers and night time resource is 8 helpers, and calender is 18hrs per day ?
Thanks in Advance
What would be maximum unit per time (h/d) if my day time resource is 10 helpers and night time resource is 8 helpers, and calender is 18hrs per day ?
Thanks in Advance
Man-hour (or man-days) is the measure that is convenient for cost estimators but planning the real work we use different measures.
We determine what crew shall be used (the number of people of different specialities and the number of machines of different kind), the workloads of different crew participants (% of work time required that may be different for different crew members) and activity duration (or volume of work in physical units and crew productivity - in this case duration is calculated). Then the number of planned man-hours and machine-hours is calculated for each crew member and for activity.
Total man-hours do not supply us with required information on crew composition.
Total man-hours may lead to erroneous results when resource leveling is required.
Managers do not think in man-hours assigning people and machines to do some work, they assign quantities. And they are right.
It is not a question of the magnitude of a certain project. Man-hour is a universal and common unit and it is more specific when used properly. While Man-Day is more confusing as you need to define exactly how many hours per day, otherwise, it can always be assumed that you mean 24 hours per day. In my opinion, it is important to consider that units of scope like: m3; m2; Lm, Ea; Kg, Tons etc. must be considered discrete in the first place. And so as Man and Hour.
In mega Construction it is usually man-day.
In Manufacturing it is in man-hour.
While using the term "Practically", perhaps have room for errors, it doesn't mean that it is in error per se. Likewise, when using the unit "Man-Hour" may have room for errors, then you must consider using it practically into which may mean discretely in order to avoid errors. Men or manpower maybe paid per hour, but I guess never paid in minutes. On the other hand, men or manpower maybe used partially in terms of percentage of hours and effort, but can never be divided literally. Oh, what am I trying say? It is always in error if you see fractions and or decimals when using Man-Hour unit.
It is in error to say - When you were using the unit Man-Hr, practically, it should always be whole number(s) i.e. OneMan/OneHour.
You shall distinguish between renewable resource quantity, consumable resource quantity, workload, effort, production rate and volume of work.
When you were using the unit Man-Hr, practically, it should always be whole number(s) i.e. OneMan/OneHour. When you get fractions or decimals (as a result of a computation, whether or not using a machine),then it would mean that perhaps you have considered minutes in your calculations and or you have considered half or perhaps 25% of a Man. It's very easy to spot errors especially when its obvious.
In turnaround and shutdown jobs it is not uncommon for many activities to be of short duration while spanning several shifts. Because activities will move fast and prompt response is necessary updating at minimum will be on daily basis if not after every shift. To manually adjust all activities considering their shifts in production rates and execution time can be a monumental task. A good model should take care of such adjustments at a single click of the mouse.
To split activities into separate tasks (one for every shift) will not make it as you do not know in advance what will be the work done by each team as the distribution of work shifts among teams with different production rates.
To get it right you will have to iterate the calculations until you match each activity start considering how predecessor duration impact every activity. Calculation of a single activity iteration takes time, imagine iterating everything until everything matches, it is not a practical approach. Why not let the computer consider all relationships at a single click?
OOPS forgot to add a row for activity duration per day. Because the overlap of teams activity duration rolls up to 26.32 hours, this is easy!
The need for shifts in construction jobs pale in comparison with the need for shifts in turnaround and shutdown jobs.
You cannot go wrong with math. So if you are not sure about the results when calculating with machines, you can always do it manually. And obviously the example given are all wrong.
You can try yourself a simple scenario, so simple it consist of a single activity.
Activity 1A 400 cm rock excavation
1 ea Resource 1 production/resource 10 cm/hr and works Monday 10 hrs, Tuesday 10 hrs and Wednesday 8 hrs/day
2ea Resource 2 (as a team) production/team 30 cm/hour and works on Wednesday 8 hrs, Thursday 8 hrs and Friday 10 hrs/day
If activity starts on Monday it will take 26.32 hours to perform the assigned volume of work.
If activity starts on Wednesday it will take 11.20 hours to perform the assigned volume of work.
Of course it will work the same irregardless of the number of activities and or resources. It all depends on how you model it in the first place. If you started wrong then so as the results.
Yes..I tried and it is working. But still not confident wheather it will work in big project or not.
Try to model it in a sample project and see for yourself and kindly give feedback to us. One thing for sure, the software will just distribute equally resources quantities and units against your defined "planning unit". I suggest you use Hours as planning unit and or duration as well, as you got two 9-hour shifts. And make sure that calendars were properly defined and assigned for each shift respectively. And of course granulate your activities, to avoid overlapping as this may create over allocation of resources.
Thank you guys. I am too much convinced with your replies and Honestly it was a great help.
Thanks again.
But one thing is creating confusion. If i am creating calender for both shift then is that so, that i have to create two separate resources with day and night suffix.(e.g.Helper_Day Shift, and Helper_Night Shift). And then assign this calender to both the resources. And when I assign the resource to activities I will assign both irrespective of shif primavera will adopt any resource automatically as per the shif.
Please Correct me if I am wrong.
then there is your answer 8
90 and 72 Respectively.
Day Crew = 9hrs x 10 labor = 90hrs/day
Night Crew = 9hrs x 8 labor = 72hrs/day
Zoltan
Nobody is working 18 hours per day:
both the day-timers and the night-timers are working on a 8 hour shift, there are 10 day-timers and 8 night-timers;
the working day amplitude is 18 hours, not the maximum units per time;
Adab should create 2 calendars, or 2 calendar shifts, one for the day time, the other for the night time
Alexandre
Maximum duration per unit time? H/D - Do you mean hours/day? I don't really understand but maximum would be 24 hours per day, beyond that would be another day. Like "Tomorrow" always coming but never arrives. I guess this is the problem when you are not sure of what "Planning Unit" to use. I think consistency is the key, as perhaps you can never use several planning unit for one project. So if you use hours as planning unit, then use it all the way. When you mix it with Days, then there would be fractions: i.e. Time/Time. I guess this only works for calendars and not for units of Scope and or Resources.
you are working 18 hours per day hence 1 man day is 18 hours
Adab,
I assume you are working on 8 hour shifts, either day or night
Solution 1:
day-time helpers and night-time helpers are two different resources; you should enter 80 h/d for day-time and 64 h/d for night-time
Solution 2: day-time helpers and night-time helpers are one unique resource; you should enter 80 h/d and make sure you assign only 64 h/d at night.
Zoltan,
I agree with Vladimir, where does your figure 18 come from ?
Alexandre
Zoltan, please explain.
In Spider Project we would enter 10 helpers in the first shift and 8 in the second shift. Shifts would have their own calendars with 9 hours work day but with different work time. Everything as in the real life.
Adab wrote about 18 hours per day work calendar and you suggest to plan for 18 helpers. It means that all 18 helpers work for 18 hours per day. This is certainly not right or I just don't understand how P6 calculate project schedules.
18