My manager has asked me to show 3 baselines on one bar. Shown me the output
One bar for one activity, with 3 colours per baseline overlapping to show delay - rather than the usual stack arrangment
Hi
My manager has asked me to show 3 baselines on one bar. Shown me the output
One bar for one activity, with 3 colours per baseline overlapping to show delay - rather than the usual stack arrangment
glad I could help
Worked it out. Filter the bars by PS and CD
[[wysiwyg_imageupload:6193:]]
Thank you
In poorly explaining it.
I know I need to filter the bars....so you can only see the delay
then put them all on the same row number. this is not the correct way to do it but its your call i am just telling you how to do what you want.
Cheers. Oh. The picture isn't there...
I do want them overlapped
I want one bar that goes up to a point with the baseline date, then goes further with the update and to the end with the last update (poorly explained I know)
1st maintain and assign 3 baselines
then in the gantt area right click bars and select the primary baseline, the seconday basline and the tertiary basline
make sure that each of these has their own row number (listed under Pattern) or they may be on top of one another.