'Multiple Float Paths' with P6 Web locks up

Do you use the 'Multiple Float Paths' functionality within the scheduler of P6 Web (EPPM)?  

I'm using R8.2 (B0869) 12.13.2011.1223 and am finding that it locks up (wont re-schedule using a new target milestone), after a single use.  It can only be unlocked by either re-scheduling with 'no float paths', or by remotely re-scheduling the same project in P6 Professional (PPM) and screen re-freshing the Web version.

If anyone is aware of this being a known (and possibly patched) issue, I would be very appreciative.