Hi everybody,
I got involved in delay analysis on motorway project, the Contract is under FIDIC Harmonised (MDB). We as Contractor received the contractual drawings on time, but from our side the submission was delayed 2 months beyond planned date in the Baseline programme.
My question is could the lack of right of way cause delay on the preparation and submission of road working drawings?
And what is the crusial information should have to prepare working drawings?
Any help appreciated..
Ok, I'll search for that.
Thank you again.
Hi Abdulrahman
That is beyond my remit.
You will need to seek professional advice.
Best regards
Mike T.
Many thanks Mike,
I would like to ask if its possible to back up the lack of coordiantes of right of way, by making refference to some external document may be there are standards of preparation woking darwings?
NB: there are no referrence to link between rigth of way and preparation of working drawings in the GCC & PCC of the project.
Hi Abdulrahman
Then in my opinion you have a strong case for an EoT on the basis of late instruction / information provided you asked for the information in good time.
Best regards
Mike Testro
Hi Mike,
Thanks for reply
The client is responsuible to provide coordinates of right of way, from local state authorities.
At the date of preparation of working drawings, we had been provided with centerline of the road and benchmarks.
Hi Abdulrahman
The key question is who was resposible for securing the right of way.
This is a common problem with linear projects such as roads and pipelines crossing land that has ownership disputes or common rights.
Best regards
Mike Testro